Sleepers start to take their place

More than 80,000 sleepers for the Borders Railway are on site, ready to be positioned along the route.

Over 90,000 will be put in place ahead of the main rail installation phase, due to start next month.

Hugh Wark, project director, said: “What has been a construction site for the last 18 months is starting to look like a railway.”